PROJECT UPDATES
August 5, 2010
NRG Energy Acquires 290-Megawatt Agua Caliente Solar Project from First Solar. press release
July 7, 2010
Order accepting the Interconnection Agreement and established an effective date of 07.28.10
June 3, 2010
The California Public Utilities Commission approved Power Purchase Agreement with Pacific Gas & Electric Company on June 3, 2010
May 28, 2010
Interconnection Agreement executed and filed with the Federal Energy Regulatory Commission
April 28, 2010
On April 28, 2010, NextLight and First Solar announced a definitive agreement for First Solar to acquire NextLight. First Solar is a leading manufacturer of PV solar panels and provider of solar solutions. The acquisition brings a number of benefits to the project, including First Solar’s advanced thin film technology and its engineering, procurement, and construction expertise. press release
April 28, 2010
Construction contract for early site work completed and early site work in progress; switchyard rough-grading and off-site road improvements to be completed by September 2010.