Project Overview

The proposed Beryl Solar Farm is located approximately five kilometers west of Gulgong, NSW and will provide significant economic and environmental benefits, in addition to creating direct and indirect jobs and developing skills in a growing industry, and supporting small businesses.

Approximately 950,000 First Solar thin film photovoltaic (PV) modules will power the proposed 95 megawatt (MW) project and will produce enough solar energy to serve the needs of approximately 28,000 average NSW homes. This will displace more than 183,000 metric tons of carbon dioxide (CO2) emissions per year — the equivalent of taking about 49,000 cars off the road.

First Solar is committed to the communities in which it operates and will strive to minimise environmental impact while maximising clean energy output. When in operation, our systems generate electricity with no water use, no air emissions, and no waste production, with the smallest carbon footprint of any PV technology available.

The proposed Beryl Solar Farm supports Australia in its efforts toward providing 23.5 per cent of its energy from renewable resources by 2020, while further establishing regional NSW as a leader in renewable energy. Planning for the project has commenced and is on track for completion in 2017.

 

Project Benefits

Enough to power 28,000 average homes

  • Displaces 183,000 tons of CO2 emissions annually—equivalent to taking 49,000 cars off the road
  • Lowest environmental impact of any PV technology
  • No water used for electricity generation
  • Significant economic and environmental benefits for regional NSW

 

Community Commitment

First Solar is committed to the communities in which it operates, including Mid-Western Region We will always engage neighbors, community groups, environmental groups and business organisations to ensure that Beryl Solar Farm remains a valued and respected member of community.

The Beryl Solar Farm will support the local and regional economy, creating direct and indirect jobs and developing skills in a growing industry, and supporting small businesses. It will generate approximately 150 construction jobs as well as ongoing full time positions. Wherever possible, First Solar seeks to partner with local businesses and suppliers. 

 

Planning Updates and Activities

First Solar has submitted an application for the Secretaries Environmental Assessment Requirements (SEARs) to the Department of Planning for the proposed Beryl Solar Farm on 23 December 2016. Following this, the Department of Planning assessed our application and issued SEARs for the project on 25 January 2017. The submission of the formal Development Application is the next step in the planning process.

The Development Application for the proposed Beryl Solar Farm was submitted to the Department of Planning Friday, 24 March.

The application is available to view on the Department of Planning’s website and will be on public exhibition next month: http://www.majorprojects.planning.nsw.gov.au/index.pl?action=view_job&job_id=8183.

Comments on the proposed Beryl Solar Farm can be submitted to Department of Planning and information on the process is available from the below link: https://www.planningportal.nsw.gov.au/understanding-planning/major-projects.

 

Environment

First Solar projects strive to minimise environmental impact while maximising clean energy output. When in operation, our systems generate electricity with no water use, no air emissions, and no waste production, with the smallest carbon footprint of any PV technology available.

 

For question or comments, please click here.

 

Type:

Single-Axis Tracking

Owner:

First Solar, inc.

Developer:

First Solar, inc.

Number of Modules:

950,000

  • 183,000Tons C02 Displaced Annually
  • 28,000Homes Powered
  • 49,000Cars Removed